Managing a Concrete Pour
When ordering a pump please give the following information:
- Company name. Contact name & telephone number of the pour supervisor.
- Delivery address including post code.
- Date & Time for the pump. (Allow 1 hour for the pump to set up ).
- Reach required
- Quantity & concrete mix including any admixtures, fibres etc.
- Description of the pour e.g. footings, slab, walls , etc.
- Any additional pipeline required.
To ensure a safe & efficient pump
pour:
- A level area of hard standing is required with no overhead obstructions, for the pump to set up.
- Clear access to the pump for the truck mixers.
- A competent concrete gang to lay the concrete.
- A suitable place for the operator to wash out at the end of the job. At least 1/ 3 mtr of concrete will be left in the pump after the pumping operation.
- A good supply of water will help the operator, although the pump does carry its own supply.
The sequence
of a typical pump
pour:
- The pump will arrive on site and the operator will liaise with the contractor before setting up.
- The concrete mixer truck will arrive and back onto the pump.
- The pump operator will grout the line and commence pumping. It is good practice to pump grout to waste, not into the pour.
- The concrete will be placed into position using the boom where possible .Where ground-line is used, the concreting gang will need to move the pipeli ne around as the pour progres ses.
- Caution: Concrete is pumped at high pressure. All personnel should be made aware of the risks and dangers associated with the end usage.
- When the truck mixer has discharged its load, the mixer chutes will be cleaned before the mixer leaves.
- The next mixer will arrive, back up and discharge its load.
- At the end of the pour, the pump operator will clean all the concrete from the pump and pipeline. This can take up to 1 hour. The boom will be put back into its travel position along with all the ancillary equipment onto the pump.
- The job sheet will be prepared for the contractor to sign and the pump will leave the site and travel back to the depot.
Quality products backed by a professional service - Readymix Concrete / Concrete Pumps / Liquid Screed